Gabritsa Wind Park

192 MW wind
437 000 million tonnes CO2 abatement

Introduction

Gabritsa Wind Park is one of the large-scale renewable energy projects which provides enough electricity to power around 142 000 homes and displaces 437 000 tonnes of carbon dioxide each year.

The park also brings economic benefits to the local municipalities – Hitrino and Venets, as well as to Shumen province, including the creation of new jobs during the stages of construction of the park and during its operation.

Gabritsa Wind Park will assist the government achieve its commitment to the European Commission in reaching 27% renewable energy in the energy mix by 2030.

Gabritsa Wind Park is part of CWP – a leading renewable energy sources (RES) project developer in Southeast Europe and Australia. Over the past 15 years we invest in the field of sustainable development and energy transition, and we are currently developing a total of 2 000 MW of RES capacities in four countries in the region – Bulgaria, Serbia, Romania and Ukraine. This way we contribute to the provision of affordable green energy, accelerated replacement of expensive and polluting power plants and the reduction of dependence on oil and natural gas. Our company has realized more than 1 500 MW of projects in Europe and Australia with a total funding of over 3,5 billion euros, including the largest wind parks in Serbia (158 MW) and Romania (600 MW). Our company works actively with local communities in Bulgaria and is a major participant in a number of social initiatives such as “Young Innovator”, Scholarship Fund “Go, Study and Come Back”, Operation “Teddy Bear” – an initiative for disadvantaged children and young people.

About the Project

The project has planned the installation of up to 24 wind turbines and associated infrastructure on agricultural land approximately 25 km north of the city of Shumen – in the Hitrino and Venets municipalities. The site is well suited to wind generation due to its reliable wind resource, suitable terrain and proximity to existing transmission infrastructure.

A range of turbine sizes are being considered for the project. The dimensions of the wind turbines anticipated to be on the market in the next few years are with height of up to 180 m (from the base of the turbine to its hub), with generating capacity of up to 8 MW. Larger turbines enable greater energy generation from a smaller number of generators, lowering the levelized cost of energy.

Gabritsa wind park will generate enough electricity to power around 142 000 homes.

 

 

Location

Gabritsa wind park is in north-eastern Bulgaria in the Hitrino and Venets municipalities, Shumen Province. The site spreads over the land of the following villages – Bliznatsi, Gabritsa, Drentsi, Kalino and Chernoglavtsi, about 25 km away from the city of Shumen.

Timeline

2022
Wind measurement campaign start
2022
Municipal urbanism completed
2022
Environmental monitoring completed​
2023
Approval of Environmental Impact Assessment (EIA)

Completion of project urbanism for the wind turbines and substation of the wind park
2024
Preliminary grid connection agreement
2025
Completion of project urbanism for roads and grid connection infrastructure

Building permit for wind turbines
2026
Design completion​

Ready to build​ (all components)
2026
Financial close
2028
Commissioning

Project Documentation

CWP is committed to developing its projects the right way.  In line with this, Gabritsa Wind Park is being constructed and operated in accordance with all relevant approvals and regulations.